Project Details

About This Project

The Nissen Reservoir Drainageway project is a crucial initiative undertaken by the City and County of Broomfield in partnership with the Mile High Flood District (MHFD). With Naranjo Civil Constructors as the prime contractor and ICON as the design engineers, this project aims to enhance flood control and drainage infrastructure from Tennyson Street to just upstream of Lowell Blvd. The project addresses a narrow channel and wide floodplain impacting local businesses and public safety. The team will protect the community and ensure a safer, more resilient future by improving drainage capacity and preventing flooding during significant precipitation events. The collaborative effort will mitigate the risk of flood damage, enhance public safety by preventing the overtopping of Perry Street, and comply with environmental regulations to preserve local ecosystems. This partnership demonstrates a solid commitment to sustainable infrastructure and community well-being.

Notice of Street Closure: Perry Street (Nissen Reservoir Phase 1)

Location: Perry St. between W 120th Ave and W 121st Pl

Roadway Opening Target: July 18, 2025 (weather dependent)

Estimated Project Completion: Mid to Late August 2025 (estimated)

Perry Street remains closed for construction related to the Nissen Reservoir Phase 1 project. The current target for roadway reopening is July 18, weather permitting. The final asphalt surface may be placed under flagger control after that date. Remaining work will continue through mid-to-late August, including trail, irrigation, and channel restoration efforts. A detour is in place for public safety. Access is limited to residents and businesses directly on Perry Street. All other traffic should follow posted detour signage.

View Detour Map and Traffic Control Plan

For Questions or concerns, please contact:

Cameron Stevens

Client Experience Manager

Naranjo Civil Constructors

cstevens@naranjocivil.com

(970) 481-1599

Project Details

Enhance Flood Drainage Infrastructure

Improve Drainage Capacity

Prevent Flooding During Heavy Rainfall

Mitigate Risk of Flood Damage

Major Work Items

Renovate Narrow Channel

Address Wide Floodplain

Prevent Overtopping of Perry Street

Comply With Environmental Regulations to Preserve Local Ecosystems

PROJECT SHOWCASE VIDEO

Weekly Project Progress Video.

PROJECT SHOWCASE VIDEO

Weekly Project Progress Video.

CAD OVERLAY

Engineer’s project designs overlaid onto current site conditions.

CAD OVERLAY

Engineer’s project designs overlaid onto current site conditions.

View Now

PROGRESS BEFORE / AFTER

Visualize the differences that have taken place on site.

PROGRESS BEFORE / AFTER

Visualize the differences that have taken place on site.

PreCon
09/24/2025